Sports Direct Head Office at Shirebrook

Client:
Sports Direct

Cube’s role:
Project Management and CDM-C

Procurement:
Existing Client

Sports Direct required a two storey, 20,000 ft extension to their head office at Shirebrook, Mansfield along with refurbishment of existing areas and fit-out of new areas.  A factory outlet shop would be at ground floor level.  The second floor supplying bespoke accommodation for a Nike International Training Academy, along with large auditorium for staff conferences plus administration suites. 

The project was allocated a 16 week timeframe, which needed to be delivered without detriment to the daily activities of staff and visiting customers.

Cube’s Approach:
The project required meticulous planning, with special attention given to the live environment.  This included control of noise, dust, safety of customers, staff and contractors alike in the immediate vicinity and surrounding areas.  Car parking needed to be restricted and safe access for deliveries arranged. 

Cube managed the design, cost and planning process alongside the Health and Safety Plan.  The programme was closely managed, ensuring a smooth delivery by all parties involved and culminating in the project finishing on time and within budget.

Testimonial

Once again, Cube didn’t disappoint; their professionalism and attention to every detail ensured a successful project was delivered with minimum disruption to head office and neighbouring businesses.